Highlights
  • Recent CAISO reforms have halted the interconnection queue in 2025; the projects that were sited in California and entered the queue were outside of CAISO’s territory.92 As of the end of 2025, just 1.4 GW of total generation and storage capacity were seeking connection to the grid in California, a steep drop compared to the past. About half of the project capacity that entered the queue in 2025 (650 MW) are of unspecified technologies, with the rest coming from standalone or hybrid energy storage projects (350 MW), solar (300 MW), solar and battery hybrid (25 MW), and gas (35 MW). On the other hand, 101 projects totalling 39 GW — all but two (which were under LADWP’s jurisdiction) that previously entered CAISO’s interconnection queue — were withdrawn in 2025. Most of these withdrawn projects previously sought interconnection during CAISO’s Clusters 11 to 15 windows.
  • Overall active queue volume decreased from 248.7 GW from the end of 2024 to 177.9 GW by the end of 2025, representing a drop of 28.5%. Most of the projects that were active before 2025 but were no longer active by the end of 2025 were withdrawn. Active queue volume fell for most technologies except for standalone solar (+9.7%), gas (+5.3%), and other (+1,622.2%).93 Solar and battery hybrid projects totaled 100 GW in 2025 and made up over half of the active queue volume (56.3%), followed by standalone battery projects (29.2%), wind and battery hybrid projects (3.9%), and standalone solar projects (3.1%). All other technologies made up the remaining 7.5% of active queue volume.
  • As of the end of 2025, projects withdrawn from the interconnection queue totaled 571.6 GW, up 73.4 GW or 14.7% from the end of 2024. Withdrawn solar and battery hybrid projects totaled 154.1 GW or 27.0% of all projects withdrawn by capacity by the end of 2025, followed by standalone battery projects (135.4 GW or 23.7% of the total), standalone solar projects (98.4 GW or 17.2% of the total), standalone gas projects (58.1 GW or 10.2% of the total), and standalone wind projects (46.6 GW or 8.1% of the total).

92 The interconnection queue increases when the pace in which projects are coming online is slower than the pace in which projects are added to the development pipeline. CAISO covers about 80% of California’s grid and a small portion of Nevada’s grid. The rest of California not under CAISO’s territory are serviced by other entities such as small and multi-jurisdictional utilities (e.g., PacifiCorp), public utilities (e.g., Sacramento Municipal Utility District (SMUD), and Los Angeles Department of Water and Power (LADWP)), and other electric service providers (ESPs).

93 “Other” is all other resources not defined in the underlying data file from the Lawrence Berkeley National Laboratory’s Queued Up research project.